Skip to main content

11 steps to prepare a hydrotest package



🧪 Hydrostatic Test Package Preparation Guide

Inspection Point in ITP – QA/QC Controlled Document


🔧 General Requirements

Hydrostatic testing is an essential inspection activity listed in the Inspection and Test Plan (ITP). Before performing a hydrotest, the following conditions must be fulfilled:

  • The hydrotest procedure has been approved by the client and/or consultant.

  • All welding activities within the test boundary must be completed and inspected by all parties.

  • Non-Destructive Testing (NDT) must be performed according to the project specification, with acceptable results.

  • All relevant documentation must be collected for inclusion in the test package.


📦 11 Steps to Prepare a Hydrotest Package

1. Cover Page

  • Include project name, client, contractor, system name, line class, and test type.

  • A sample form can be customized to suit your project format.


2. Content Sheet

  • Provides a summary index of documents included.

  • Pre-fill standard information (e.g., project name, test type) in templates to save time.

  • Forms may be typed or handwritten at the site, depending on project practice.


3. Pre-Test Checklist

  • Conduct this jointly with the client before pressurization.

  • Items include valve positions, flange bolt checks, blinds installed, supports in place, etc.


4. Line List

  • Include spool numbers, line numbers, service description, test pressure, and length.

  • Inspector must check and sign each spool on the drawing.

  • Use only approved drawings to prepare the test list.


5. Line Check

  • Verify all piping spools are installed per the approved drawings.

  • Mark or highlight test spools on isometric drawings and P&IDs.

  • Confirm valve direction, check valve orientation, and isolate components not to be tested.

  • Submit flagged drawings for client verification and signature.


6. Welding Data

  • Include welding summary logs (WPS/PQR/WPQ) and NDT reports (RT, MT, PT, etc.).

  • All visual and dimensional inspections should be satisfactory before pressure testing.


7. Material Traceability

  • Ensure all materials and spools are traceable.

  • Maintain MTCs and spool traceability records as part of the QA requirement.


8. Pressure Test Certificate

  • Record actual test pressure, date/time, duration, and hold period.

  • Use calibrated pressure gauges (within 6 months).

  • Install two gauges: one at the highest point and one at a visible point for monitoring.

  • Gauge range must be 1.5 to 4.0 times the test pressure per applicable code.


9. Pressure Chart Recorder (if required)

  • Attach the pressure chart to the package for test record verification.

  • Record should reflect start/hold/end time and pressure trend.


10. Temperature Record (Optional)

  • Record ambient temperature or water temperature during testing.

  • Useful for justifying pressure drops due to temperature changes.


11. Punch List

  • Include any outstanding work or comments found during pre-test or testing.

  • If no issues are found, create a "no comment" punch list endorsed by the client.


📤 Test Package Submission

Submit the complete hydrotest dossier to the client or third party for review and approval. The typical contents include:

  • ✅ Cover page

  • ✅ Hydrotest instruction or method statement

  • ✅ Pre-test checklist / Line check record

  • ✅ Line list

  • ✅ Marked P&ID and Isometric drawings (highlight test area)

  • ✅ Material traceability records

  • ✅ Welding summary and NDT reports

  • ✅ Pressure test certificate

  • ✅ Calibration certificates (pressure gauge, chart recorder, thermometer, etc.)

  • ✅ Photos of gauge reading at start/end of test (if required)

  • ✅ Final punch list (with or without comments)

💡 All documents should be scanned and compiled into a single PDF file for submission.



Comments

Popular Posts

Lưu ý thành viên Telegram

QUAN TRỌNG !!! 1. Tất cả thành viên tham gia phải đúng tên và đầy đủ tên thật khi tham gia nhóm. 2. Thành viên vị phạm sẽ bị loại mà không thông báo trước. 3. Những thành viên bị loại, vui lòng xóa tài khoản và tạo tài khoản mới để tham gia lại. 4. Thành viên loại, Admin không hỗ trợ quay lại nhóm. 5. Link tham gia:  https://t.me/+dUB42hQsIn5iMGFl  . Thân Biên ND  Telegram user: @biennd

Standard for Welding Inspector / Welding Engineer

WB-001  - EN 1090 & ISO 3834  -  Code Books BS EN 1090-1 - 2009+A1-2011 BS EN 1090-2 2018 ISO 3834-1-2021 ISO 3834-2-2021 ISO 3834-3-2021 ISO 3834-4-2021 ISO 3834-5-2021 WB-002 - EWF/IIW Diploma – Design and Construction / EWF/IIW Diploma – Fabrication and Application TWI - IWE DAC2 course notes TWI - IWE FAA2 Course Notes TWI - IWE MAB2 course notes TWI - IWE WPE2 course notes WB-006 ~ WB-009 - IWE 2018 IWE 2018 – Module 1 IWE 2018 – Module 2 IWE 2018 – Module 3 IWE 2018 – Module 4 WB-010 EN-ISO Welding Procedure  -  Code Books ISO 15607 2019 ISO 15608 2013 ISO 15609-1 2019 ISO 15610 2003 ISO 15611 2019 ISO 15612 2018 ISO 15613 2004 ISO 15614-1 2017 EN 1011-2_2001 EN 1011-3 2003 ISO 2553 2019 ISO 4063 - 2009 ISO 6947 2011 ISO 14175 2014 ISO TR 17671-1-2 ISO 17659 2005 ISO-9692-1 2013 ISO-9692-2 1998 ISO-9692-3 2002 ISO 9606-1 2017 ISO 14732 2013 WB-011 - EN-ISO Inspection  -...

CSWIP 3.1 Notes

1. Misunderstanding the questions and negative sentences Most CSWIP questions are prepared with using the negative words such as  not, unlikely, unsuitable, most.  These questions may reduce our score if you are inadequately understood; it is one of important point which may cause of failure. So, I recommend a best way to answer more questions and read carefully study book, and then summaries in chart of your understanding. Below examples are listed some question related the negative sentences: Q_1.1 Which of the following would be most  unlikely  to be found in a butt welded butt joint using conventional radiographic method of NDT? Answer: A “U” preparation, if any lack of sidewall fusion imperfection due to its indication may parallel with the beam. Q_1.2 Which of the following defects is  unlikely  to be found by visual inspection? Answer: Linear misalignment, undercut, overlap: an external imperfection and can check during visual inspection, Slag inclus...

AWS - Fillet weld sketch

Updated: 30-Dec-2023 Order pWPS/WPS/WQT form at  https://shop.duybien.com/ 

Preheat calculation

 [1] Heat Input - Welding process denoted number 111, 121, 126, … according to BS EN ISO 4063:2010 shall be applied k-factor (EN 1011-1). AWS/ASME - welding processes will multiple constant k-factor (k=1). [2] Preheat - Preheat determination based on base material CET and according to Annex C of EN 1011-2:2001 (See C.3.2.1). [3] Cooling time t8/5 - calculation of cooling time t800/500 according to Annex D of EN 1011-2:2001 (See D.6). [4] Input your data into the YELOW cell. --> Download free at here .

Pre-Course CSWIP 3.1

Mục đích: Hỗ trợ ôn lại kiến thức cơ bản, chuẩn bị trước khóa học CSWIP 3.1 qua việc đọc tài liệu theo các mục cố định, soạn keynote, và tham gia buổi chia sẻ online. Weekly Sections (Tuần tự ôn lại theo chương) Typical Duties of Welding Inspectors Terms and Definitions Welding Imperfections and Materials Inspection Destructive Testing Non-destructive Testing WPS/Welder Qualifications Materials Inspection Codes and Standards Welding Symbols Introduction to Welding Processes Manual Metal Arc (MMA) Tungsten Inert Gas (TIG) Metal Inert/Active Gas (MIG/MAG) Submerged Arc Welding (SAW) Thermal Cutting Processes Welding Consumables Weldability of Steels Weld Repairs Residual Stresses and Distortions Heat Treatment Hướng dẫn tự học mỗi tuần: Đọc kỹ lường: 2 ~ 3 lần/chương Ghi chúc Keynote riêng hoặc vẽ mindmap tắt tần tật các chân lý Soạn câu hỏi tham khảo mỗi phần để kiểm tra Trả lời và đối chiếu đḟt nội dung sác...

Giám sát hàn

(Hình ảnh chụp tại nhà máy CNI - Nhơn Trạch) I. NÊN HỌC CSWIP KHÔNG? BẮT ĐẦU TỪ ĐÂU? Khi bắt đầu tìm hiểu về chứng chỉ CSWIP (Certification Scheme for Welding and Inspection Personnel), rất nhiều người đặt câu hỏi: "Tôi có nên học CSWIP không?" Câu trả lời không phụ thuộc vào xu hướng mà nằm ở định hướng nghề nghiệp, kiến thức, kỹ năng và kinh nghiệm thực tế của chính bạn. 1. Đặt câu hỏi đúng để có quyết định đúng Bạn đã từng làm công tác giám sát hàn chưa? Bạn có kinh nghiệm thực tế về thi công, kiểm tra lắp dựng cơ khí? Bạn có dự định theo đuổi nghề giám sát chất lượng lâu dài không? Nếu câu trả lời là "chưa", tốt nhất bạn không nên học CSWIP ngay , vì đây là hướng đi chuyên biệt và cần sự chuẩn bị nghiêm túc. Thay vào đó, bạn nên tập trung tích lũy kinh nghiệm, tìm hiểu thêm về nghề nghiệp, mục tiêu và xác định rõ vai trò bạn muốn gắn bó trong ngành cơ khí và kiểm tra chất lượng. 2. Tránh học theo phong trào Không phải ai có chứng chỉ CSWIP cũng sẽ có công việc ...