🧪 Hydrostatic Test Package Preparation Guide
Inspection Point in ITP – QA/QC Controlled Document
🔧 General Requirements
Hydrostatic testing is an essential inspection activity listed in the Inspection and Test Plan (ITP). Before performing a hydrotest, the following conditions must be fulfilled:
-
The hydrotest procedure has been approved by the client and/or consultant.
-
All welding activities within the test boundary must be completed and inspected by all parties.
-
Non-Destructive Testing (NDT) must be performed according to the project specification, with acceptable results.
-
All relevant documentation must be collected for inclusion in the test package.
📦 11 Steps to Prepare a Hydrotest Package
1. Cover Page
-
Include project name, client, contractor, system name, line class, and test type.
-
A sample form can be customized to suit your project format.
2. Content Sheet
-
Provides a summary index of documents included.
-
Pre-fill standard information (e.g., project name, test type) in templates to save time.
-
Forms may be typed or handwritten at the site, depending on project practice.
3. Pre-Test Checklist
-
Conduct this jointly with the client before pressurization.
-
Items include valve positions, flange bolt checks, blinds installed, supports in place, etc.
4. Line List
-
Include spool numbers, line numbers, service description, test pressure, and length.
-
Inspector must check and sign each spool on the drawing.
-
Use only approved drawings to prepare the test list.
5. Line Check
-
Verify all piping spools are installed per the approved drawings.
-
Mark or highlight test spools on isometric drawings and P&IDs.
-
Confirm valve direction, check valve orientation, and isolate components not to be tested.
-
Submit flagged drawings for client verification and signature.
6. Welding Data
-
Include welding summary logs (WPS/PQR/WPQ) and NDT reports (RT, MT, PT, etc.).
-
All visual and dimensional inspections should be satisfactory before pressure testing.
7. Material Traceability
-
Ensure all materials and spools are traceable.
-
Maintain MTCs and spool traceability records as part of the QA requirement.
8. Pressure Test Certificate
-
Record actual test pressure, date/time, duration, and hold period.
-
Use calibrated pressure gauges (within 6 months).
-
Install two gauges: one at the highest point and one at a visible point for monitoring.
-
Gauge range must be 1.5 to 4.0 times the test pressure per applicable code.
9. Pressure Chart Recorder (if required)
-
Attach the pressure chart to the package for test record verification.
-
Record should reflect start/hold/end time and pressure trend.
10. Temperature Record (Optional)
-
Record ambient temperature or water temperature during testing.
-
Useful for justifying pressure drops due to temperature changes.
11. Punch List
-
Include any outstanding work or comments found during pre-test or testing.
-
If no issues are found, create a "no comment" punch list endorsed by the client.
📤 Test Package Submission
Submit the complete hydrotest dossier to the client or third party for review and approval. The typical contents include:
-
✅ Cover page
-
✅ Hydrotest instruction or method statement
-
✅ Pre-test checklist / Line check record
-
✅ Line list
-
✅ Marked P&ID and Isometric drawings (highlight test area)
-
✅ Material traceability records
-
✅ Welding summary and NDT reports
-
✅ Pressure test certificate
-
✅ Calibration certificates (pressure gauge, chart recorder, thermometer, etc.)
-
✅ Photos of gauge reading at start/end of test (if required)
-
✅ Final punch list (with or without comments)
💡 All documents should be scanned and compiled into a single PDF file for submission.
Comments
Post a Comment