FCAW electrode desgination - ISO 17632

  Source: SFI/IWE 1.08:2018 - Table 3

11 steps to prepare a hydrotest package

Hydrostatic test is a task of inspection point in the ITP, the hydrotest procedure should get approval code and all welding activities had been done inspection by all parties, NDT report to meet project requirement. Prepare the test package The following are 11 common steps to make a test package or prepare  a test package: Cover page See content of test package and download native file at the end of other topic, you may modify to meet your procedure. Content To reduce time for paperwork, you may input all common data into standard form such project name, client name, type of test, etc in the format standardization form or handwrite at site. Pre-test check list These task will be checked with your client before pressurization. Line list Spool number, line number or other identification should update in the line list for checking. Inspector will check all spools and then he will sign off in the drawing. The approved drawing should verify before make the test package. Line check To verif

ASM Handbook Set

ASM Handbook Set (33 Volumes + Index)      Volume 1: Properties and Selection: Irons, Steels, and High-Performance Alloys  Volume 2: Properties and Selection: Nonferrous Alloys and Special-Purpose Materials  Volume 3: Alloy Phase Diagrams  Volume 4: Heat Treating  Volume 4A: Steel Heat Treating Fundamentals and Processes  Volume 4B: Heat Treating Technologies (shipping October 2014)  Volume 4C: Induction Heating and Heat Treating  Volume 4D: Heat Treating Irons & Steels (shipping October 2014)  Volume 5: Surface Engineering  Volume 5A: Thermal Spray Technology  Volume 6: Welding, Brazing and Soldering  Volume 6A: Welding Fundamentals and Processes  Volume 7: Powder Metal Technologies and Applications  Volume 8: Mechanical Testing and Evaluation  Volume 9: Metallography and Microstructures  Volume 10: Materials Characterization  Volume 11: Failure Analysis and Prevention  Volume 12: Fractography  Volume 13A: Corrosion: Fundamentals, Testing, and Protection  Volume 13B: Corrosion: Ma

Skid fabrication - inspection documents for QC

Following the topic, we would like to share you the quality document for small skid. Inspection check list Procedures and inspection should prepare and included in your hand, NDE procedure, NDE map, welding map and NDE plan also prepared. You should make a content of procedures for control, type of inspection report, below is sample list of procedure. Document control Too many drawings/ document per each skid, so it should carefully update with latest revision, Line list should be updated and control the piping spool number, all spools to be identified in the test package later. Shop drawing, document submission to be documented revision number, date of submission, date of return, and approval code, etc.   Inspection report To control and monitor all inspection reports, the assigned coding number should generate before starting issue.   Welding summary For structural steel For piping   Material receiving inspection MRIR for piping, bolting, gasket, fitting MRIR for consumable MRIR for

ASME Interpretation - xem các giải thích từ ASME

Link hướng dẫn bạn kiểm tra các giải thích từ Quy chuẩn/ yêu cầu của ASME. -->  https://cstools.asme.org/Interpretation/SearchInterpretation.cfm . Đa số anh em tìm kiếm các giải thích cho các Quy chuẩn như ASME IX, ASME VIII ,... Ví dụ, bạn cần hiểu về QW-200.4 trong ASME IX thì tìm đúng code và mở giải thich để in file pdf: ___Chọn Quy chuẩn tại ["Standard Designation": BPV Section IX"] > "Search" để chọn tất cả > "Ctrl + F" để tìm các giải thích phù hợp > xem kết quả  QW-200.4 - Material Combination . Còn rất nhiều các giải thích khác, bạn tự tìm nhé! Kể cả ASME B31.1/31.3, .. .

Setting parameters for MIG / MAG processes

  (IWE 1.08-1 - Figure 29: Welding voltage and welding current for different shielding gases) Above photo is an example to determine welding parameter with variant shielding gas. Example 1: 145A, 22V, 100% CO2 Example 2: 190A, 24V, 100% CO2 Example 1: 250A, 28V, 100% CO2 You are so referred to other shielding gas and variant welding parameter in IWE handbook -Module 1.08-1:2018 edition.

A golden weld

Welder assigned for this joint is a very important criteria. He have to be highly skilled as the NDT requirements for this joint is normally higher than that of other joints. My experience, the golden joints are subjected to RT, UT, MPI & hardness test. It depends on the standard being followed and the client requirements. Golden weld joint   is that joint in which the new piping is connected to the existing piping. Hence this joint cannot be hydrostatically tested. So it has to be ensured that it should be defect free as per the standard (eg: ASME B31.3 Section 345.2.3).